Tuesday, May 31, 2011

Wood Walls Delivered and Started



This weekend's trip revealed that the wood walls had been delivered and the builder got started with one wall. Hopefully this is going to lead to bigger and brighter things on the road to completion.

Saturday, May 21, 2011

Insulation Complete



The insulation was completed and inspected but not without a week's delay. The walls around the chimney required a special kind of insulation which the builder had to special order. Even though he anticipated it, he didn't get it ordered with the initial shipment. Walls here we come!

Sunday, May 8, 2011

Insulation Begins



Insulation arrived and the builder has started the job. Should all be finished and inspected by Tuesday.